At A Glance

Client: Avondale Waste Ltd
Architect: Unknown
Main Contractor: Lend Lease
Location: Falkirk
Products: Kingspan CW, WV & RW composite panels
Value: £1.74m
Completed: Dec 2011

Curtis Moore has completed the roofing and cladding works at the Avondale Waste Treatment plant in West Lothian. The works comprised the supply and installation of over 10,000 Sq.m of Kingspan Products installed over a 14-week programme.
 
A total of 10,500 Sq.m. of Kingspan KS1000 RW was installed to the roof area, with 9,500 sq.m. of panels being installed to the vertical walls. Wall cladding was a combination of KS 1000 Microrib and Longspan panels, which were, installed using 360 Roto’s and vacuum lifting equipment. Included in the scope of Curtis Moore’s works was the supply and installation of vertical secondary steel framing and the roof safety system and walkways.