Our team on the HM2 turbine hall at Hinkley Point C has been rolling 56-metre Kalzip standing seam roof sheets at ground level, then lifting them onto the roof on a 60-metre beam.
That’s a single roof sheet longer than an Olympic swimming pool, lifted on an even longer beam.
Why roll on site?
Rolling the sheets beside the building means:
- no road transport limits on sheet length
- no end laps across the roof
- a continuous, weathertight roof from eaves to eaves
Where we are on HM2
HM2 follows the handover of the HM1 turbine hall envelope in March 2025. We’re delivering Kalzip 65/400 roofing and cladding to both turbine halls for BYLOR, with the HM2 envelope due for completion in early Q4 2026.
Huge credit to the team on site for planning and delivering every lift safely